Mechanic's liens · State comparisonMechanic's lien deadlines by state: how long after the work a lien can appear, and how long it lasts

A contractor or supplier who wasn't paid can still record a lien for a while after the last work – including after a sale – so the filing window is what a TC checks against the seller's recent projects. In these twenty states and D.C. the window is measured like this: 90 days in Florida (Fla. Stat. §713.08), Washington (RCW 60.04.091), Connecticut (Conn. Gen. Stat. §49-34), Maine for claimants without a contract with the owner (10 M.R.S. §3253), North Dakota (N.D. Cent. Code §35-27-13), Montana (MCA 71-3-535) and D.C., after completion (D.C. Code §40-301.02) and for full effect in Iowa (Iowa Code §§572.10–572.11); 90 days from the end of the month of last work, and no later than 90 days after completion, in Virginia (Va. Code §43-4); 120 days in North Carolina (N.C.G.S. 44A-12), Minnesota (Minn. Stat. §514.08), South Dakota (SDCL 44-9-15) and Alaska unless a notice of completion shortens it (AS 34.35.068); four months for a contractor and three for a subcontractor in Kansas (K.S.A. 60-1102, 60-1103); 150 days for a contractor and 120 for others in Wyoming (W.S. 29-2-106); 180 days after completion for a contractor and 120 days for others in Delaware (25 Del. C. §2711); 180 days after final completion, or 90 after a notice of completion, in Utah (Utah Code §38-1a-502); 90 days after completion, or 60 days for a direct contractor and 30 for others after a recorded notice of completion, in California (Cal. Civ. Code §§8412, 8414); eight months after the last work – four months for a single-family dwelling – in New York (N.Y. Lien Law §10); on Texas residential projects, the 15th day of the third month after the month the work was completed (Tex. Prop. Code §53.052); and six months after the debt accrued in Missouri (RSMo 429.080). Once filed, a lien must be enforced by suit within a limit – for example one year after the last item in Minnesota (§514.12), eight months after recording in Washington (RCW 60.04.141), six months after recording or 60 days after completion in Virginia (§43-17), six months after filing in Missouri (RSMo 429.170), one year after filing in Kansas (K.S.A. 60-1105), 90 days after recording in California (Cal. Civ. Code §8460), one year after filing in New York unless extended (N.Y. Lien Law §17), one year after recording with a lis pendens in Connecticut (§49-39), 120 days after the last work in Maine (10 M.R.S. §3255), six months after recording in Alaska (AS 34.35.080), two years after filing in Montana (MCA 71-3-562), 180 days after filing in Wyoming (W.S. 29-2-109) and 180 days after the notice of intent in D.C. (D.C. Code §40-303.13). Some states add notice systems that limit liens: a lien agent in North Carolina and on Virginia one- and two-family permits, an online registry in Iowa, and pre-lien notices in Minnesota.

The states

  1. Florida (ch. 713)

    Claim of lien within 90 days after final furnishing; lapses after one year without suit.

  2. North Carolina (ch. 44A)

    Claim within 120 days after last furnishing; lien agent for projects of $40,000 or more.

  3. Texas (Prop. Code ch. 53)

    Residential: affidavit by the 15th day of the third month after completion; bills-paid affidavit at closing.

  4. Missouri (RSMo ch. 429)

    Lien within six months after the debt accrued; suit within six months after filing.

  5. Minnesota (§514.08)

    Statement recorded and served within 120 days; suit within one year.

  6. Iowa (ch. 572)

    Online registry; full effect within 90 days; suit within two years after them.

  7. Virginia (§43-4)

    Memorandum within 90 days from the end of the month of last work; suit within six months.

  8. Washington (RCW 60.04.091)

    Claim within 90 days after last furnishing; suit within eight months.

  9. Kansas (K.S.A. 60-1102)

    Contractor within four months, subcontractor within three; suit within one year.

  10. South Dakota (SDCL 44-9-15)

    Statement within 120 days; owner's demand forces suit within 30 days.

  11. Maine (10 M.R.S. §3255)

    Action within 120 days after the last work; buyer takes free of an unrecorded lien.

  12. Connecticut (§49-34)

    Certificate within 90 days, served within 30 more; foreclosure and lis pendens within a year.

  13. North Dakota (§35-27-13)

    10-day warning, recording within 90 days; a late lien doesn't bind a good-faith buyer.

  14. Montana (MCA 71-3-535)

    Notice of right within 20 days; filing within 90 days; suit within two years.

  15. Alaska (AS 34.35.068)

    Claim within 120 days (15 after a notice of completion for some); lien lasts six months without suit.

  16. Wyoming (W.S. 29-2-106)

    Contractor 150 days, others 120; preliminary notices required; suit within 180 days.

  17. Washington, D.C. (§40-301.02)

    Notice of intent within 90 days after completion; suit within 180 days plus a lis pendens.

  18. Delaware (25 Del. C. §2711)

    Contractor 180 days after completion, others 120; judgment relates back to the start of work.

  19. Utah (§38-1a-502)

    Notice within 180 days after completion (90 after a notice of completion); suit within 180 days or void.

  20. California (Civ. Code §§8412, 8414)

    90 days after completion, or 60/30 days after a notice of completion; suit within 90 days.

  21. New York (Lien Law §10)

    Eight months after the last work – four for a single-family home; one year to foreclose.

What the TC checks in any state

  • Whether the seller had work done within the state's filing window.
  • Lien waivers or releases from the contractor and subcontractors, and any bills-paid affidavit the state or contract uses.
  • Any recorded lien – sent to the title company before closing.

Questions about mechanic's lien deadlines

Can a contractor file a lien after I buy the house?

Yes, within the state's window after the last work – for example 90 days in Florida and Washington, 120 days in Minnesota and North Carolina – which is why recent work and lien waivers matter before closing.

How long does a mechanic's lien last if nobody sues?

It depends on the state: one year after the last item in Minnesota, eight months after recording in Washington, and six months after filing in Missouri, among these states.

Add a task in ClosingCode for lien waivers from recent contractors, with an owner and a due date before closing.

Start free trial

Sources: Fla. Stat. §713.08; N.C.G.S. 44A-12; Tex. Prop. Code §53.052; RSMo 429.080, 429.170; Minn. Stat. §§514.08, 514.12; Iowa Code ch. 572; Va. Code §§43-4, 43-17; RCW 60.04.091, 60.04.141; K.S.A. 60-1102, 60-1103, 60-1105; SDCL 44-9-15, 44-9-26; 10 M.R.S. §§3253, 3255; Conn. Gen. Stat. §§49-34, 49-39; N.D. Cent. Code ch. 35-27; MCA 71-3-531, 71-3-535, 71-3-562; AS 34.35.068, 34.35.080; W.S. 29-2-106, 29-2-109; D.C. Code §§40-301.02, 40-303.13; 25 Del. C. §§2711, 2718; Utah Code §§38-1a-502, 38-1a-701; Cal. Civ. Code §§8412, 8414, 8460; N.Y. Lien Law §§10, 17 (official state sites, read for the linked guides).

General information, not legal advice. The title company decides how a lien affects the title policy. ClosingCode is software; it is not a law firm or title company. This guide is not a substitute for the advice or services of an attorney.