Washington, D.C. · D.C. Code §§40-301.02, 40-303.13D.C. mechanic's lien deadlines: the 90-day notice of intent and the 180-day suit
In the District of Columbia, a contractor that wants to enforce a mechanic's lien records a notice of intent in the land records during construction or within 90 days after the earlier of completion or termination of the project; if it doesn't, the lien terminates when the 90 days run out, and a notice missing the required contents is void (D.C. Code §40-301.02(a)(1)). The contractor sends a copy to the owner by certified mail within five business days after recording, or posts it on the property if the mail comes back (§40-301.02(a)(2)). A subcontractor's or supplier's lien is limited to the amount still due to the original contractor, and if the owner in good faith paid the original contractor in full, they have no lien – unless they notified the owner in writing of amounts due while the owner still owed the contractor at least that much (§40-303.02). A lien is enforced only by filing suit within 180 days after the notice of intent is recorded and recording a notice of pendency of action within 10 days of filing; otherwise the lien terminates (§40-303.13).
The deadlines
1. Notice of intent (§40-301.02(a)(1))
During construction or within 90 days after completion or termination.
2. Copy to owner (§40-301.02(a)(2))
Certified mail within 5 business days after recording.
3. Subcontractors (§40-303.02)
Limited to the unpaid contract balance; barred after good-faith full payment.
4. Suit (§40-303.13)
Within 180 days, plus a lis pendens within 10 days of filing.
What the TC can do
- If the seller had work done within the filing window, ask for lien waivers from the contractor and subcontractors.
- Send any recorded lien to the title company before closing.
- Keep the waivers in the deal file.
Questions about mechanic's liens
How long does a D.C. contractor have to record a mechanic's lien?
The notice of intent is recorded during construction or within 90 days after the earlier of completion or termination of the project (D.C. Code §40-301.02(a)(1)).
How long does a D.C. mechanic's lien last?
It terminates unless suit is filed within 180 days after the notice of intent is recorded and a notice of pendency is recorded within 10 days of filing (§40-303.13).
Related guides
Add a task in ClosingCode for lien waivers from recent contractors, with an owner and a due date before closing.
Start free trialSource: D.C. Code §§40-301.02, 40-303.02 and 40-303.13 (code.dccouncil.gov, read October 26, 2026).
General information, not legal advice. The title company decides how a lien affects the title policy. ClosingCode is software; it is not a law firm or title company. This guide is not a substitute for the advice or services of an attorney.