Oklahoma · 42 O.S. §§141–178Oklahoma mechanic's lien deadlines: four months, 90 days for subcontractors, and the pre-lien notice

A contractor files a verified lien statement with the county clerk within four months after the date materials or equipment were last furnished or labor last performed under its contract (42 O.S. §142). A subcontractor, supplier or worker under a contractor files within 90 days after it last furnished materials or labor, and until those 90 days run the owner bears the risk of payments made to the original contractor (§143). Before filing, a claimant other than the original contractor sends a pre-lien notice to the original contractor and an owner no later than 75 days after its last supply; a lien on a dwelling occupied by the owner isn't valid without that notice, though the notice isn't otherwise required for non-owner-occupied residential projects of up to four units or claims under $10,000 (§142.6(B)). A lien is enforced by a civil action brought within one year after it was filed (§172).

The deadlines

  1. 1. Contractor (§142)

    Lien statement within four months after the last work.

  2. 2. Subcontractor (§143)

    Within 90 days after its last work; owner's payments at risk until then.

  3. 3. Pre-lien notice (§142.6)

    Within 75 days after last supply; required for owner-occupied homes.

  4. 4. Suit (§172)

    Within one year after the lien is filed.

What the TC can do

  • If the seller had work done within the filing window, ask for lien waivers from the contractor and subcontractors.
  • Send any recorded lien to the title company before closing.
  • Keep the waivers in the deal file.

Questions about mechanic's liens

How long does an Oklahoma contractor have to file a lien?

Four months after materials were last furnished or labor last performed under the contract (42 O.S. §142).

Does an Oklahoma subcontractor need to send notice before filing a lien on my home?

Yes – for a dwelling the owner occupies, a lien isn't valid unless the pre-lien notice was sent within 75 days after the claimant's last supply (42 O.S. §142.6(B)(1)).

Add a task in ClosingCode for lien waivers from recent contractors, with an owner and a due date before closing.

Start free trial

Source: Oklahoma Statutes Title 42 §§142, 142.6, 143 and 172 (oklegislature.gov, read October 26, 2026).

General information, not legal advice. The title company decides how a lien affects the title policy. ClosingCode is software; it is not a law firm or title company. This guide is not a substitute for the advice or services of an attorney.